Solar Philippines Tanauan Corporation (SPTanC) filed an Application dated 05 February 2020 (Application), seeking the Energy Regulatory Commission’s (ERC) approval of its authority to develop and own dedicated point-to-point limited transmission facilities to connect the Naic Solar Power Plant to the MERALCO TMC 2 Substation. SPTanC seeks to ensure the unhampered supply of electricity, particularly in Luzon.
The ERC is scheduled to hear the Application on September 16, 2020 at nine o’clock in the morning.